Which authority approves your Hyderabad building now that GHMC is three corporations, how BuildNow and Bhu Bharati replaced TG-bPASS and Dharani, and the NALA, lake and LRS checks, with official links.
Before you rely on any of this: Hyderabad's approval system changed a great deal in 2025 and 2026. This guide was updated in October 2026 for those changes, and everything below links to its source. Confirm the current position on the official portal, or with an architect who has recently filed in your area, before you spend money or sign anything. This is a plain-English guide, not legal advice.
To build a house in Hyderabad you need two separate things: a clean land record from the Revenue Department, and a building permission from the municipal corporation or development authority for your area. Both are now online, and for an ordinary house on a plot of up to 500 sq m the building permission can be issued instantly on self-certification.
What has changed is the map. The building portal is now BuildNow, not TG-bPASS; land records are on Bhu Bharati, not Dharani; and GHMC has grown and then been split in three. If you last looked in 2024, most of the names you remember are out of date.
Since 2025 there are four possible answers.
If a seller cannot tell you which of these applies, treat that as a warning sign. Our plot due diligence checklist covers the other checks to run before you pay.
Two documents matter. The Telangana State Building Permission Approval and Self-Certification System Act, 2020 (Act 12 of 2020, published in the Telangana Gazette on 19 September 2020) sets up the self-certification system and its thresholds. The Telangana Building Rules, 2012 (G.O.Ms.No.168, dated 7 April 2012, as amended) set the setbacks, heights and other parameters. Both are on the BuildNow GOs and Acts page. For what setbacks and FAR mean in practice, start with our explainer on setbacks, FAR and height limits.
Dharani is gone. The Telangana Bhu Bharati (Record of Rights in Land) Act, 2025 came into effect on 14 April 2025 and superseded the 2020 law behind Dharani (The South First). The new Bhu Bharati portal went live the next day and the Dharani portal was deactivated, as Deccan Chronicle reported. The same report says the Act provides a tiered appeal route through the RDO, the Collector and a land tribunal.
Before you pay anything, run two free checks on the portal:
Converting agricultural land is still governed by the Telangana Agricultural Land (Conversion for Non-Agricultural Purposes) Act, 2006, known as the NALA Act, which requires a conversion tax before agricultural land is put to non-agricultural use. The Act is listed on the Chief Commissioner of Land Administration's Acts page. Unlike Maharashtra and Karnataka, Telangana has not folded conversion into building approval: we found no 2025 or 2026 amendment that does so in the official sources we checked.
What has changed is where you file. Conversion is now applied for on Bhu Bharati, which offers an "Application for NALA" service, a version for land without a passbook, and an "Application for Pending NALA" for land converted before Bhu Bharati that still shows as agricultural. According to the official FAQ, the system calculates and shows the NALA charges to be paid before you book a slot, so take the figure from the portal rather than from a rate someone quotes you. The BuildNow timelines page lists NALA conversion by the Revenue Department at 14 days when it runs alongside a building file.
Conversion and permission remain separate: a NALA order is not a building permission, and a building permission does not convert your land record.
BuildNow is now the portal for building and layout applications within GHMC, HMDA and DTCP limits. Its notice told applicants to submit pending TG-bPASS applications by 15 December 2025, after which the TG-bPASS portal would close permanently. The tiers still come from the 2020 Act.
| Plot and building | Route | Published timeline |
|---|---|---|
| Up to 75 sq yd (63 sq m), ground or ground plus one, residential | No permission needed; register online with a ₹1 token and self-certify title, plot size and floors | 15 days |
| Up to 500 sq m and 10 m high, residential | Instant approval on self-certification | 15 days |
| Above 500 sq m and above 10 m, and all non-residential | Single window, with all NOCs on one common application | 21 days |
The thresholds come from section 7 of the Act and the TG-bPASS information page, and the timelines from BuildNow. The BuildNow flow chart splits the instant tier at 200 sq m: larger plots up to 500 sq m, with up to stilt plus three or ground plus two floors, are approved instantly but with a mortgage. Its checklist asks for a front-side site photograph and your sale deed with link documents, and for a plot in an unapproved layout, a document registered before 26 August 2020.
Self-certification makes the approval fast, and it puts the risk on you. Section 7 of the Act says the onus to ensure the self-certification is authentic lies with the applicant, who is personally accountable for a false declaration. The owner also signs an undertaking that construction in violation of the sanctioned plan can be demolished without any notice. That is why the architect who prepares your drawings matters: they are the one making sure that certificate is true. If you are planning a 30x40 or similar plot, our guide to what you can build on a small plot shows how the rules shape it.
The Hyderabad Disaster Response and Asset Protection Agency (HYDRAA) was set up by G.O.Ms.No.99 and covers the whole of CURE, all three corporations. Its about page lists protecting lakes, nalas and public land from encroachment as a core function. The rules it enforces come from the Building Rules, 2012, as BuildNow's line departments page sets out:
Before you buy near water, look up the lake on the HMDA lakes portal, which lists preliminary and final FTL notifications and the survey numbers affected. A January 2026 order, G.O.Ms.No.16, added a rule granting transferable development rights for land affected by FTL, maximum flood level and buffer zones, with their use within CURE, so owners of such land have a route other than building on it.
If the plot is in an unapproved layout, it needs regularising before it can get a building permission. The Layout Regularization Scheme 2020 (G.O.Ms.No.131, 31 August 2020) is the scheme in force, and its FAQ says plainly that without regularisation no building permission will be given. In 2026 the state offered a 25 per cent rebate on LRS fees for people who applied in 2020 and still had dues to pay. It opened on 1 May and was due to close on 31 July (Deccan Chronicle, 27 July 2026), and was then extended to 30 November 2026 (Deccan Chronicle, 31 July 2026). We found only press reports of the extension, not the order, so confirm it on the LRS portal. We found no Building Regularisation Scheme (BRS) window open for new applications in October 2026.
BuildNow's published timelines set out when you need an Occupancy Certificate (OC):
The Act also exempts the 75 sq yd tier from an OC. The TG-bPASS site notes that permissions are post-verified, so build exactly to the sanctioned plan. For a realistic budget once approvals are in hand, see our Hyderabad construction cost breakdown.
The law is, the portal is not. The TG-bPASS Act, 2020 still sets the self-certification tiers, but new applications go through BuildNow, and BuildNow's notice said the TG-bPASS portal would close permanently after 15 December 2025.
No. Bhu Bharati replaced it on 14 April 2025, and land status, the prohibited properties list and NALA conversion are now on the Bhu Bharati portal.
It depends on the zone. Cyberabad has Serilingampally, Kukatpally and Qutbullapur; Malkajgiri has Malkajgiri, Uppal and L.B. Nagar; GHMC keeps the other six zones, including Charminar, Khairatabad and Secunderabad.
No. Ownership does not lift the rule: no building is allowed in the FTL or the buffer zone. A January 2026 rule allows transferable development rights for such land, which is the legal way to get value from it.
You can browse architects practising in Hyderabad on MOA, see their published work and message them directly, with no commission on either side.