Who sanctions your building in Kolkata: KMC, Howrah, NKDA or the municipality. Plus land conversion, the 500 sq m land ceiling NOC, fire thresholds and the completion certificate, with official links.
Before you rely on any of this: rules, fees and portals in West Bengal change often. This guide was updated in October 2026, when KMC had just grown to 209 wards and the state had promised, but not yet passed, a repeal of the Urban Land Ceiling Act. Everything below links to its source. Confirm the current position with the authority or an architect who has filed there recently. This is a plain-English guide, not legal advice.
In Kolkata, who sanctions your building depends on which body governs the plot: Kolkata Municipal Corporation (KMC), Howrah Municipal Corporation, the New Town Kolkata Development Authority (NKDA), or one of the municipalities around them. Plans are filed online by a licensed professional. Before that, two land checks catch people out: converting land still recorded as agricultural, and a land ceiling clearance for plots of 500 sq m or more.
The Kolkata Metropolitan Development Authority (KMDA) does not sanction houses. It is the planning authority for the metropolitan planning area and prepares the Land Use and Development Control Plans (LUDCPs) that say how land may be used. If a seller cannot tell you which body governs the plot, treat it as a warning sign; our plot due diligence checklist covers the other checks.
KMC's FAQ on its Common Application Form lists the prerequisites: the BL&LRO mutation and conversion certificates, the land ceiling NOC, a property tax NOC, and clearances where trees, water bodies or heritage are involved. The state's municipal checklist adds the registered deed and, where it applies, development permission under the West Bengal Town and Country (Planning and Development) Act, 1979; in Salt Lake Township, the Final Possession Certificate too. So the order is: deed, mutation in your name, then everything else. The land department's portal is Banglarbhumi.
Change of land use is regulated by sections 4A to 4D of the West Bengal Land Reforms Act, 1955. The state's guidance on conversion says you apply after mutation, with the deed, an up-to-date rent receipt, the mutation certificate and a map of the plot and its neighbours. Its FAQ sends applications to the Block Land and Land Reforms Officer for up to 10 decimals, the Sub-divisional officer for up to 1 acre and the District officer above that. A field enquiry and a hearing follow; neighbours' NOCs have not been needed since 2015.
The guidance cites orders up to 2015 and its fee table covers conversion to industrial and commercial use, so ask the land reforms office for the current fee. We found no 2025 or 2026 reform of the conversion process.
Rule 4(4) of the KMC Building Rules says that where the plot is 500 sq m or more and the Urban Land (Ceiling and Regulation) Act, 1976 applies, the application must carry a no objection certificate from the Competent Authority under that Act. UDMA says the 2007 municipal rules require the same. At 720 sq ft to the katha, 500 sq m is roughly 7.5 katha.
Will it go away? Finance Minister Swapan Dasgupta said on 26 June 2026 that the state will scrap the Act (Swarajya) and repeated on 2 October 2026 that it "has to go" (NewKerala). Neither report mentions a bill, and we found no repeal notified as of 16 October 2026. Until there is one, budget for the NOC.
Only a KMC-empanelled Licensed Building Surveyor (LBS) or architect can apply, on the owner's behalf, through the online Common Application Form, which also routes outside NOCs such as fire, pollution control, the airport authority and KMDA. The FAQ gives 15 days for those NOCs and 30 days for sanction from the date of application. Who must sign depends on the building (rule 47):
Fees. KMC's schedule for 2026-27 sets a one-time application fee for a home on a plot of up to 500 sq m of ₹2,000 up to 7 m high, ₹5,000 up to 10 m and ₹11,000 up to 12.5 m. The permit fee then depends on covered area and road width, with multipliers by use and extra charges for wet work, stacking and drainage. A permit is valid for at least five years and can be renewed up to ten years in all (rule 15).
e-Grihanaksha grades each file as low, medium or high risk. Under the state's risk classification (gazetted February 2023), a house for your own use of up to 400 sq m built-up and 10 m high, on shallow foundations with nothing underground, is generally low risk and needs an LBS. Drawings go through an auto-scrutiny engine, and for low-risk files UDMA's procedure runs from scrutiny and payment straight to a digitally signed permit. The state fee schedule starts at ₹500 for the first 30 sq m of a home for own use plus ₹75 per further 10 sq m; Salt Lake Township charges ₹3.50 per sq ft for residential plots.
NKDA asks for a registered architect and an enlisted engineer, and documents including the registered deed, the memorandum of possession, the mutation certificate and paid-up property tax.
UDMA's circulars page lists an amendment of the KMC Building Rules dated 4 September 2025, but the file returned "not found" on 16 October 2026, so we have not summarised it. It also lists a June 2026 order adopting the National Building Construction Standards 2026 in place of the 2016 National Building Code under the municipal rules. Ask your architect how either affects your plot, and see our explainer on setbacks, FAR and height limits.
| Authority | Fire Services clearance needed for |
|---|---|
| KMC (rule 129) | every building except a residential building under 15.5 m without a basement |
| Municipalities on e-Grihanaksha | residential above 15.5 m, residential with a basement at any height, and every non-residential building |
| NKDA, New Town | any non-residential building, any building over 15.1 m, or any plot over 1,500 sq m |
A basement changes the answer for a house in KMC and the municipalities.
Plinth. KMC's FAQ says the plinth-level intimation is mandatory. Under rule 24, an officer inspects within seven days of your notice. e-Grihanaksha handles plinth and occupancy stages online for municipalities.
Completion. In KMC, the completion notice is due within a month of finishing, countersigned by your LBS or architect and structural engineer, with completion plans and a structural stability certificate (rule 27). KMC inspects within 15 days and issues the certificate within ten days of inspection if the work matches (rule 28). Without it there are no municipal water or drain connections, and no one may occupy the building (rule 32). NKDA issues an occupancy certificate through OBPAS. For how long all this adds to a build, see our stage-by-stage construction timeline.
Once the sanction is in hand, our Kolkata construction cost breakdown helps you set a realistic budget.
Neither, for building sanction. NKDA sanctions New Town plans through its OBPAS portal. Salt Lake is part of Bidhannagar and files through e-Grihanaksha.
Only if the plot is 500 sq m or more. The state has said it will scrap the 1976 Act, but no repeal had been notified as of 16 October 2026.
KMC's FAQ gives 15 days for outside NOCs and 30 days for sanction from the date of application. It also says details cannot be corrected after final submission and a plan not in order is rejected, so a clean first file matters most.
Only after conversion under the West Bengal Land Reforms Act, and only if the land use plan allows it. East Kolkata Wetlands land needs separate sanction.
No. In KMC only an empanelled LBS or architect can file; NKDA requires a registered architect and an enlisted engineer.
Approvals go faster with someone who has filed with your authority before. Browse architects on MOA, see their published work and message them directly, with no commission on either side.