ABPAS 3.0 step by step: the new portal address, login and registration, deemed approval up to 186 sq m, documents, fees with a worked example, status checks and downloading the permission.
Before you rely on any of this: ABPAS 3.0 moved to a new web address in April 2026, and the Madhya Pradesh Bhumi Vikas Rules, 2012 have been amended many times since they were made, most recently in 2025 and 2026. This guide was written on 2 November 2026 from the portal itself, its user manuals and the rules, and every fee and timeline below links to its source. Rules and charges change, so confirm them for your plot with your architect or the ABPAS helpdesk before you pay or build. This is a plain-English guide, not legal advice, and nothing here guarantees an approval.
ABPAS 3.0 is the Automated Building Plan Approval System that Madhya Pradesh's Urban Administration and Development Department runs for building permission in its cities and towns. It now lives at abpas.mpurban.gov.in. A registered architect or licensed engineer files the case online, software checks the drawing against the rules, and the permission comes back digitally signed. For a house, three things decide how fast that happens: the plot size, whether the layout is approved, and how clean the drawing is.
This guide covers the portal itself. For the land side (diversion, the Development Plan), read our Indore building permission guide. A Bhopal guide is coming soon.
The Madhya Pradesh Bhumi Vikas Rules, 2012 (BVN) say that where the authority has adopted an online system, the application, plans, documents and fees can only be submitted through that software, and the licence and plan are certified by digital signature (rule 14(1), in the TNCP consolidation of the rules up to 6 March 2025). In Madhya Pradesh's urban local bodies, that system is ABPAS 3.0. The department's own website sends its building permission link there, and the portal's fee schedule describes itself as applicable in all ULBs of the state.
Besides building plan approval, the portal handles completion cum occupancy, colony development permission, approvals in MPIDC and MSME areas, and nine case types from new construction (Erect) to alteration, demolition, boundary walls, revalidation and compounding.
Two things sit outside it. Development permission for land in a planning area (subdivision, change of use, larger projects) comes from the Directorate of Town and Country Planning under rule 2(5)(a). And if your plot is under a gram panchayat rather than a municipal body, ask the panchayat which route applies before you assume ABPAS. Note too that on 28 August 2026, according to TeamLease RegTech, rule 2(5)(c) was amended so a local body can permit construction on plots of up to 500 sq m that conform to the approved Development Plan without a separate development permission. I could not open that gazette text.
Old links no longer work. A notice on the portal says the earlier domain, abpas3.in, was shut down from 1 April 2026 and moved to abpas.mpurban.gov.in. Many guides, and the state's single-window instructions, still point to abpas3.in.
Under rule 18, the architect, structural engineer, engineer, supervisor or town planner prepares and signs every plan with their name, address, qualifications and licence number, and the owner signs too. Rule 26 says an architect registered with the Council of Architecture needs no separate licence from any authority and may submit plans for buildings of any size; structural engineers, engineers and supervisors are licensed by the authority (₹1,500 for an engineer, ₹750 for a supervisor, valid for three years), each within the competence the rule sets. A supervisor, for example, is limited to houses on plots up to 200 sq m and two storeys. You can check an architect's registration on the Council of Architecture register.
The ABPAS 3.0 user manual for consultants sets out the sign-up:
The portal also has a citizen registration, which asks for a Samagra ID. According to the state's ABPAS 3.0 instructions, a case filed from a citizen login does not need the owner's authorisation letter to the consultant. The drawing still needs a qualified professional's signature under rule 18.
The consultant manual's FAQ says a blocked account unlocks after 20 minutes. For a lost user ID or password, the portal's header lists a toll-free helpline, 1800 120 2664, and the email abpas.helpdesk@wisseninfotech.com.
Whatever the route, the drawing must meet the Bhumi Vikas Rules on setbacks (marginal open spaces), FAR and height. Our explainer on setbacks, FAR and height limits walks through those terms.
This is the sequence in the consultant manual and the erect-case manual for a new house.
The state's ABPAS 3.0 instructions list five mandatory documents and a set of conditional ones, and rule 16 of the BVN describes what the drawings must show.
ABPAS reads a colour-coded CAD file: a layer for each floor, and each element (plot boundary, setbacks, rooms, parking) drawn as a line, polyline or text in the colour the Smart DCR user manual specifies. Our guide to the drawing set your architect should hand over explains how a submission set differs from working drawings.
The portal publishes a standard fee schedule for all ULBs, which follows rule 21 of the BVN. It also says other charges, such as malba (debris), service charge, development fee and similar, are set by each local body according to the site, so your demand note will include those too.
| Fee | Basis | Rate for a house |
|---|---|---|
| Application fee | Rule 21(2)(ii), proposed built-up area | ₹1 per sq m, not refundable |
| Building permission fee | Rule 21(3)(b), built-up area slabs | ₹750 up to 75 sq m; ₹1,250 for 76 to 125; ₹2,000 for 126 to 200; ₹3,000 for 201 to 300; ₹4,000 for 301 to 400 |
| Water harvesting fee | Plot area 140 sq m or more (letter of 27 October 2009) | ₹7,000 for 140 to 200 sq m; ₹10,000 for 200 to 300; ₹12,000 for 300 to 400; ₹15,000 above |
| Karmakar fee | Letter No. 6-12/2007/18-3 of July 2007 | 1% of the estimated construction cost; houses for self-use costing under ₹10 lakh are exempt |
| Revalidation | Rule 21(3)(b), item 9 | 10% of the original permission fee |
Worked example (illustrative). A 150 sq m plot (about 1,615 sq ft) in an approved colony, with a ground-plus-one house of 180 sq m built-up area (about 1,940 sq ft), and a cost estimate of ₹36 lakh on the form:
The karmakar fee is the biggest item and scales with the cost estimate. For a budget for the build, try MOA's home cost calculator. Under rule 21(3)(d), the authority may reject the application if the permission fee is not deposited within 15 days of the intimation to pay.
Anyone can track a file on the portal's Application Tracking page, which covers ABPAS 2.0 and 3.0 files and searches by file number, owner name, applicant or consultant name, and ULB.
Once signed, the architect downloads the sanction letter, drawing PDF, drawing .dxf and scrutiny report from the consultant console. Ask for all four. The consultant manual's FAQ says a building permission is valid for three years, and that an expired one is extended by filing a revalidation case on ABPAS.
These are targets; returned files and missing NOCs add time.
Rule 31 makes the owner responsible for building to the sanctioned plan. On ABPAS the architect files four intimations: commencement, plinth, service level and completion cum occupancy; the inspector fills a checklist, the CMO approves, and each certificate downloads from the portal, as its occupancy flow chart shows. Rule 31(2)(h) says that if the authority neither issues the occupancy certificate nor asks for changes within 30 days of your request, it is deemed issued. Our stage-by-stage construction timeline shows where these fall in a typical build.
Deviations matter. Rule 24 rules out any deviation from the sanctioned plan that affects the front setback, parking, the road line or a water body, or that exceeds 30% of the permissible FAR. Building without or beyond permission means compounding: for a house, the portal's fee schedule sets five times the permission fee for work within the permissible limits and 5% of the value of the extra built-up area for up to 10% over, and anything beyond that has to be removed before it can be compounded.
abpas.mpurban.gov.in. The portal says the old abpas3.in domain was shut from 1 April 2026. Sign in with the system-generated user ID issued after your registration was approved.
You can register as a citizen with a Samagra ID and track files, and the state's instructions allow a case through a citizen login. But the drawing must be a colour-coded CAD file prepared and signed by a COA-registered architect or a licensed engineer or supervisor, so in practice your architect or engineer files it from their own login.
On the portal's Download page: a consultant manual, a manual for each case type (erect, alteration, revalidation and others) and the Smart DCR manual on how to draw for the scrutiny engine.
The permission fee itself is ₹750 to ₹4,000 for most houses, by built-up area, plus ₹1 per sq m as application fee. Water harvesting (plots of 140 sq m or more) and the 1% karmakar fee usually cost more, and local bodies add their own charges.
Three years, according to the consultant manual. After that, file a revalidation case on the portal; the fee is 10% of the original permission fee.
An architect who has filed on ABPAS recently already knows its drawing format and document list. Find a COA-verified architect on MOA and choose your city in the city filter.