What BU permission and the plot validation certificate are under CGDCR 2017, how to apply with AMC, SMC or VMC, the fee and 21-day rule, getting a copy, and where SUDA's DP 2035 stands.
Before you rely on any of this: this guide was checked on 2 November 2026 against Gujarat's Comprehensive General Development Control Regulations (CGDCR) 2017 and the notifications listed by the state's Town Planning and Valuation Department. Rules, fees and portals change, and a July 2026 draft change to CGDCR is still pending. Every point links to its source. An architect or the authority's help desk can confirm what applies to your plot. This is a plain-English guide, not legal advice, and no guide can promise an approval.
BU permission is Gujarat's occupancy certificate. "BU" stands for Building Use, and under CGDCR 2017 nobody may use or occupy a building until the authority has granted it. The plot validation certificate sits at the other end of the same file: it fixes your plot's net area and boundary before you apply for permission to build. Both come from the same authority, AMC, SMC or VMC inside the three cities and AUDA, SUDA or VUDA around them, and both are set out in Part I of CGDCR.
For the full approval process in each city, see our guides to building permission in Ahmedabad, Surat and Vadodara.
Regulation 3.8 of CGDCR 2017 Part I (the Procedure Regulations, as notified on 3 October 2019) makes it mandatory to obtain building use permission before a building is occupied or used. Using a building without it, in a way that does not match it, or after it has been revoked, is unauthorised use.
Under regulation 3.9.2, a BU permission means the authority accepts that the building was built to the sanctioned design and may be used for its sanctioned use. It does not certify title or ownership, structural safety, workmanship or the plot boundary. Those stay with the owner and the professionals who signed.
Other states call this an occupancy certificate, and so does AMC's own building permission procedure, which describes it as "occupancy certificate / building use permission". AMC's building plan FAQ says drainage, water supply, solid waste and electricity services can be obtained after BU permission is granted. On Gujarati forms it is usually just written બી.યુ., as on VMC's BU checklist. Our national guide to occupancy and completion certificates is coming soon.
Any building that needed a development permission needs BU before anyone moves in. A change of use needs permission too: regulation 3.9.4 bars using a building for anything other than its sanctioned use without written permission. On 8 August 2026 AMC sealed a premises in Dariyapur approved for shops and homes that was being run as a gymkhana (DeshGujarat).
The body that granted your development permission also grants the BU permission:
| City | Inside city limits | Around the city |
|---|---|---|
| Ahmedabad | Ahmedabad Municipal Corporation (AMC) | AUDA |
| Surat | Surat Municipal Corporation (SMC) | SUDA |
| Vadodara | Vadodara Municipal Corporation (VMC) | VUDA |
SMC's approval process page (last updated in October 2019) sends low-rise, non-commercial buildings to the zone office and high-rise, commercial buildings and layouts to the central Town Development Department, and ends with the completion certificate and the grant of the occupancy certificate. The city guides linked above explain the June 2020 boundary changes.
Gujarat files building permissions on the Online Development Permission System (ODPS). The state's Town Planning and Valuation Department links ODPS to e-Nagar, and the ODPS 2.0 circular of 2 December 2020 sets up nodal officers in every corporation and authority for the online system covering both building permission and building use permission.
If a neighbouring owner or the housing society will not give consent at the BU stage, regulation 3.9.1 lets the authority grant BU after giving them a hearing. If BU is refused, regulation 3.12.3 provides an appeal committee for D1 to D7 areas, with an appeal fee equal to the scrutiny fee, capped at ₹50,000. Where fire approval is needed, it is applied for on the state's Fire Safety Compliance Portal; Schedule 11 requires a fire consultant and the Chief Fire Officer's opinion for residential buildings taller than 15 m.
CGDCR calls the professionals "persons on record": an architect on record or engineer on record, a structural engineer on record and a clerk of works on record, each registered with the authority and renewed every year. CGDCR's qualifications for an architect on record start with registration with the Council of Architecture and two years of practice, and you can check an architect's registration on the Council's register. The owner signs too, and stays responsible for using the building as approved.
Table 3.3 under regulation 3.9.5 sets the fee for use permission as a share of the development permission scrutiny fee:
The scrutiny fee itself is in Schedule 1. For residential buildings in categories D1 to D6, which include AUDA, SUDA and VUDA (Table 1.1), it is ₹10 per sq m of built-up area with a minimum of ₹1,000. CGDCR works in square metres throughout.
Worked example (illustrative): a family home with 250 sq m (about 2,690 sq ft) of built-up area pays a scrutiny fee of 250 × ₹10 = ₹2,500 at the permission stage. If it is built as sanctioned, the BU fee is 5% of that, ₹125. With internal changes only, it is ₹5,000.
Three cautions. An amendment of 11 November 2020 added a note to Schedule 1 that fees may be revised by the competent authority from time to time. AMC's own fee structure sheet, which is undated and older than the current rules, lists scrutiny fees as payable both at the development permission and at the building use application. Other charges, such as tree deposits, can be added. Take the figure the portal raises as final. Using a building without BU carries a penalty of four times the scrutiny fee for the area used (regulation 3.9.6). For the cost of the build itself, try the MOA home cost calculator or our Ahmedabad construction cost breakdown.
The only published timeline is the 21 days in regulation 3.9.1, counted from the notice of completion. AMC's procedure and VMC's FAQ repeat it. Queries add time, so a clean as-built set matters most.
Many searches ask for a BU permission download for AMC, SMC or VMC. Here is what we could verify on 2 November 2026:
Regulation 3.1 of CGDCR Part I says any development needs a written application, and adds a proviso: the applicant must hold an effective Plot Validation Certificate from the competent authority. Form 19 is its format. It is issued by the same authority that grants the permission, AMC, SMC or VMC in the cities and AUDA, SUDA or VUDA outside them, and signed by its planning assistant, surveyor or inspector. SMC's website has no separate page for it as of 2 November 2026; Surat uses the same CGDCR form.
Form 19 records the plot in one of two ways. Outside a town planning (TP) scheme it uses the zone, ward, revenue survey or block number, or gamtal city survey number. Inside one it uses the scheme name and stage, and the original plot (OP) and final plot (FP) numbers. The office then fills in the plot boundary, dimensions and area; the land deducted for TP roads and development plan (DP) roads; whether TP road dimensions are available; any court matter; a drawing; and a "valid up to" date.
The resolution of 26 April 2018 that started ODPS from 1 May 2018 adds an applicant's version, its Annexure 1. In it, you certify the net plot area to be used for the development permission, that the drawing shows the final dimensions, and that land in the setback, road line or amenity contribution has been surrendered. Its explanation sets out how the net plot is decided:
Why it matters: the net plot is the area the permission is worked out on, and it can be smaller than the area in the sale deed or the land record. See our guide to setbacks, FAR and height limits for how that area shapes the house. In a draft TP scheme the final plot can still change.
Yes. SUDA's development plans page lists the Development Plan 2035 under notification GH/V/157 of 2020/DVP-142018-5731-L of 8 October 2020, with a corrigendum, GH/V/173 of 2020, of 9 November 2020. A state notification of 27 February 2026 confirms that the Final Development Plan of SUDA was sanctioned by the 2020 notification.
Since then the plan has been changed village by village under section 19(1) of the Gujarat Town Planning and Urban Development Act, 1976. SUDA's variations page lists notifications from 9 July 2024 to 27 February 2026. The latest, GH/V/32 of 2026, proposes to realign a 30 m road through Puna and Saroli, both inside SMC, and to zone the released land residential, with two months for objections. Each is a proposal until finalised. SUDA's site shows no draft of a newer plan as of 2 November 2026.
So for a plot, a current zoning certificate and plot validation certificate count for more than an old DP sheet. Surat's FSI table and Tapi flood-line rule are in our Surat guide.
Building Use permission. It is Gujarat's occupancy certificate, granted in Form 14 under regulation 3.9 of CGDCR 2017, and it is required before a building is used.
In Gujarat, yes. AMC's procedure document uses both names for the same certificate. A completion certificate is different: it is the professional's notice that construction is finished (Form 12), which comes before BU.
CGDCR requires the authority to inspect and communicate its decision within 21 days of receiving the notice of completion. Queries stop that clock until you comply.
For a recent building, ask the architect or engineer who filed it on ODPS for the issued Form 14. We found no public BU search on AMC's website as of 2 November 2026. For an older building, apply to the AMC office that issued it with the file or final plot number.
The competent authority for the plot: SMC inside city limits and SUDA outside them. It is in the CGDCR format, Form 19, and records the net plot after road and TP deductions.
Yes, by notification GH/V/157 of 2020 dated 8 October 2020. It has been varied village by village since, most recently by a proposed variation of 27 February 2026 for Puna and Saroli.
An architect who has filed BU applications with your authority before will know its queries in advance. Find a COA-verified architect on MOA; choose your city in the city filter.