Who approves your house plan in Gurugram (HSVP, DTCP or MCG), how self-certification and the 20-day deemed sanction work under the Haryana Building Code, the fees, and what changed in 2025 and 2026.
Before you rely on any of this: Haryana's building rules changed several times in the last year, and more changes were proposed on 2 November 2026, the day this guide was written from the official texts linked below. Confirm the position for your plot with your architect or the authority's help desk before you spend money. This is a plain-English guide, not legal advice, and no guide can promise an approval.
In Gurugram, a house is approved by one of three offices depending on where the plot is: Haryana Shehri Vikas Pradhikaran (HSVP, formerly HUDA) for its sector plots, the Town and Country Planning Department for plots in licensed private colonies, or the Municipal Corporation of Gurugram (MCG) for other municipal plots. All three apply the same rulebook, the Haryana Building Code 2017.
For a house, that Code is generous. A residential plot up to 16.5 m high counts as "low risk", so a registered architect can file the plan under self-certification and you may start work as soon as it is submitted. The authority then has 20 days to decide; if it does not, a compliant plan is deemed sanctioned.
Building plan approval is the authority's written permission to build what your drawings show. It is mandatory. Code 2.1 of the Haryana Building Code 2017 (consolidated up to 13 August 2026) says anyone who intends to erect, re-erect, alter or demolish a building must first give notice to the Competent Authority in Form BR-I, with the documents listed there. Self-certification changes who checks the drawings first. It does not remove the need to file.
Delhi and Noida work differently, so advice from across the border does not carry over. Our Delhi building plan guide covers MCD and MPD-2047, and our Noida guide covers the Noida Authority's lease-based system.
If your seller cannot say which of these applies, treat it as a warning sign.
Farmland in a controlled area cannot be built on with a building plan alone. Section 7 of the Haryana Scheduled Roads and Controlled Areas Restriction of Unregulated Development Act, 1963 requires the Director's permission and conversion charges first. Within municipal limits that power rests with the Director, Urban Local Bodies (ULB Haryana SOP 02/TPCell/2024). Outside them, the department's CLU workflow applies: an online application with a scrutiny fee of ₹10 per sq m of gross site area, field reports, then a letter of intent if the site conforms to the development plan.
The Code has applied across Haryana since 6 January 2017. The changes that matter for a house in 2026:
Code 6.3(3)(i)(a) sets these limits for plotted housing outside core areas, and the building must also conform to the sector's zoning plan or architectural control sheet. For local reference, the Code's own worked example treats a 14 marla plot as 354.1 sq m and a 1 kanal plot as 505.86 sq m.
| Plot area | Max. ground coverage | Max. FAR | Max. height |
|---|---|---|---|
| Up to 100 sq m | 75% | 165% | 16.5 m |
| 100 to 250 sq m | 75% | 145% | 16.5 m |
| 250 to 350 sq m | 66% | 130% | 16.5 m |
| 350 to 500 sq m | 66% | 120% | 16.5 m |
| 500 to 1,000 sq m | 66% | 100% | 16.5 m |
Three rules people trip over: going over the ground coverage limit is non-compoundable, so it cannot be regularised by paying a fee; no balcony may project beyond the rear zoning line; and the parking table in Code 7.1 asks for 0.5 to 2 car spaces per floor depending on plot size, with stilt parking compulsory in the Gurugram Manesar Urban Complex once you build a third or fourth floor. Our explainer on setbacks, FAR and height limits shows how these numbers shape a plan.
Under the Code an "Architect" is a person registered with the Council of Architecture under the Architects Act, 1972, and Appendix A makes the architect the one who prepares and signs all building plan submissions. Self-certification means approval of plans "prepared and certified by Architect". A civil engineer may handle structural drawings and supervision for plots up to 1,000 sq m and 15 m height. Since 1 January 2026 HSVP no longer runs an annual empanelment: COA-registered architects register on its portal, which checks their details against the COA database in real time (HSVP notice of 1 January 2026).
Code 2.1(1) lists the core set:
HSVP's OBPAS user manual adds an Aadhaar card and a site, deviation or compounding report, and it will not accept a drawing until every mandatory CAD layer is present. For what a full drawing set contains, see every drawing your architect should hand over; our sanction drawing guide is coming soon.
The applicant, architect and engineer sign digitally and the file goes online (Code 2.1(3) and 2.3). Under Code 2.2 a low-risk building may start construction immediately after the application is submitted. The authority must sanction or reject within 20 days of a complete submission; a plan that conforms to the Code and the permitted land use, with all fees paid, is deemed sanctioned if no order comes in that time (Code 4.5). In licensed colonies, the department's process note says any observation on a self-certified plan is conveyed within 15 days of approval.
If a file is returned, you can resubmit within 60 days without a fresh scrutiny fee, but only twice (Code 2.1(4)). Sanction is valid for two years for a building under 15 m and five years for taller ones (Code 4.3).
The Code applies across the state and sets two fees of its own:
Worked example: a house with 290 sq m (about 3,120 sq ft) of covered area across all floors pays a scrutiny fee of 290 × ₹10 = ₹2,900. Other charges depend on the plot rather than the Code's table. The department's building plan checklist adds labour cess "depending upon class of construction", and in licensed colonies the self-certification note adds purchasable area and external development charges where due. On HSVP plots the portal works out the fee from your drawing and generates a challan before you pay, so the challan is the figure to budget for. For the cost of the build itself, see our Delhi NCR construction cost breakdown.
The DPC certificate. At damp proof course level, the architect certifies that the work matches the sanctioned plan. The authority has seven days to respond, after which a compliant certificate is deemed accepted (Code 4.9). Any change you want during construction needs a revised plan before it is built (Code 4.6).
Stilts and the road edge. After the High Court order, a Town and Country Planning order of 16 April 2026 told authorities including GMDA, HSVP and MCG to act against unauthorised use or construction in stilt floors and to remove lawns, landscaping and boundary walls built on the road's right of way. Keep the stilt for parking (the Code allows a guard room and toilet there) and keep your landscaping inside the plot line.
The occupation certificate. The Code bars anyone from occupying a new building until an occupation certificate has been issued, and no certificate is issued until debris has been cleared from the site and its surroundings. Because the architect-issued route is on hold, ask your authority which procedure it is using when you apply; HSVP handles occupation certificates for its residential plots on OBPAS. Keep the sanctioned plan, DPC certificate and occupation certificate together, because a buyer's lawyer or a bank will ask for all three.
Changing your architect. Tell the authority within seven days; work stops until the new professional takes over (Code 2.2, note iv).
Yes. Code 2.1 of the Haryana Building Code requires notice in Form BR-I before anyone builds, rebuilds, alters or demolishes a building. Self-certification lets your architect file and you start on submission, but the plan still has to be filed and must comply.
The Code gives the authority 20 days from a complete submission. If it neither sanctions nor rejects a compliant plan in that time, the plan is deemed sanctioned (Code 4.5).
The Code's scrutiny fee is ₹10 per sq m of covered area. HSVP's portal calculates the full challan from your drawing.
Not for now. The High Court stayed the policy on 2 April 2026, and the department put all such approvals on hold the next day. A Tribune report of 4 May 2026 quotes the Bench saying the entire policy is subject to the outcome of the case.
A COA-registered architect prepares and signs the plans and certifies them under self-certification. A qualified civil engineer can supervise and prepare structural drawings for plots up to 1,000 sq m and 15 m height, and taller buildings need both.
An architect who has filed on your authority's portal recently will save you weeks. Find a COA-verified architect on MOA and choose Gurugram in the city filter.