Zaha Hadid Architects' Terminal 1 at Navi Mumbai: who designed and built it, the lotus roof on 12 feature and 17 mega columns, the plan and phases, the hill cut and river moved, and the dates.
Navi Mumbai International Airport (NMIA) was designed by the London practice Zaha Hadid Architects (ZHA), which won a 12-week competition for the terminal in March 2018. Terminal 1 was inaugurated on 8 October 2025 and took its first commercial flights on 25 December 2025. Its roof is a field of petal-shaped shells on 12 sculpted feature columns and 17 mega columns, which the architects and the operator describe as drawn from the lotus. Below: brief, site, plan, structure, materials, climate, reception and lessons, with MOA diagrams.
Navi Mumbai International Airport: the facts
Architect: Zaha Hadid Architects, London (Terminal 1, the air traffic control tower and landside access). Project directors Cristiano Ceccato and Filippo Innocenti; project designer Paulo Flores (team as listed by Surfaces Reporter). Engineering: Arup (multidisciplinary engineering for the concept and scheme designs). Contractor: Larsen & Toubro (EPC). Lighting design: Lichtkompetenz and Lum Gallery (as listed by LSI).
Client: Navi Mumbai International Airport Pvt Ltd (NMIAL), a public-private partnership: Mumbai International Airport Ltd, an Adani Airport Holdings subsidiary, holds 74% and CIDCO 26%. The GVK group led the company when ZHA was appointed; the Adani Group took over in 2021.
Location: Ulwe, Pushpak Node, Panvel taluka, Raigad district, Maharashtra. Codes NMI (IATA) and VANM (ICAO).
Designed and built: competition won March 2018; inaugurated 8 October 2025; commercial flights from 25 December 2025; international flights from 15 July 2026.
Size: site of 1,160 ha. Phase 1: 20 million passengers and 0.5 million tonnes of cargo a year; 90 million passengers a year at full build-out (operator's figures).
Type: greenfield international airport; Terminal 1 is the first of the planned terminals.
Status: in use, operated by the Adani Group.
The airport is Mumbai's second, built because the existing Chhatrapati Shivaji Maharaj International Airport was running close to its limit. Dezeen (Natasha Levy, 15 March 2018) reported that ZHA won the commission after a 12-week design competition among practices shortlisted by GVK, then the lead partner. The scope was a new passenger terminal and an air traffic control tower. Prime Minister Narendra Modi had laid the foundation stone a month earlier, on 18 February 2018, and the opening was then planned for 2020.
The project is older than its design. The Adani Group's inauguration release (8 October 2025) dates Union Cabinet approval to 2007. The first environmental and CRZ clearance went to CIDCO on 22 November 2010 and a fresh one on 28 November 2021, according to the operator's compliance report for April to September 2025. Airport Technology records that the GVK-led company won the bid in February 2017, awarded the construction (EPC) contract to L&T in August 2019, and received the site in June 2022.
ZHA designed the terminal. Arup's project page says it partnered with ZHA and provided "multidisciplinary engineering and specialist services" for the concept and scheme designs, and also designed the central plant building. L&T built it: its project page lists Passenger Building 1, the south runway and associated facilities in its initial-phase scope.
Asked about the brief by the Free Press Journal (Dhairya Gajara, February 2025), ZHA director Cristiano Ceccato put function first: the terminal is a working building "with the layout driven by operational requirements". He described three terminals in all, with the third to be "effectively a mirror of Terminal 1".
The site is 1,160 ha at Ulwe, on low ground beside Panvel Creek. Of that, 933.7 ha is airside and 226.3 ha landside, according to the compliance report. It is linked to South Mumbai by the Mumbai Trans Harbour Link (Atal Setu), and ZHA's project page lists metro, suburban rail and ferry links as planned.
Before anything could be built, the land had to be made. The compliance report describes the Ulwe river flowing down from the hills to the south towards the centre of the site, and the Gadhi river, partly retrained, along its north; both drain into Panvel Creek. CIDCO's pre-development works raised the land to +5.5 m above mean sea level and diverted the Ulwe river into a channel, work the report says CIDCO completed in 2019. NMIAL's own scope was to cut the Ulwe hill and fill the site from +5.5 m to an average +8.5 m. The Moodie Davitt Report (Martin Moodie, 2 June 2025) describes a 90 m hill levelled to 8 m and about 2,500 families rehoused.
The same report gives the forest land diverted as 250.06 ha, with 108 ha of compensatory mangrove planting completed at Kolekhar, and says the main drains were designed for 148.1 mm of rain an hour, the 1-in-100-year value recommended by the Central Water and Power Research Station (CWPRS).
The lotus is how ZHA and the operator explain the building, and it is worth separating what they claim from what the roof does. ZHA's page says the terminal's forms are informed by the lotus, India's national flower, which appears throughout the country's art, architecture and literature. Ceccato told the Free Press Journal that "the lotus flower was the basis of inspiration both for the frontage of the terminals and for the main interior columns". The Adani release says the terminal roof suggests petals and that "the central atrium resembles a lotus pond".
The operator's own article on ACI Asia-Pacific (2 October 2025) goes further, calling the lotus a "guiding structural principle" rather than decoration: the petals became the roof canopies, and the unfolding flower informed the columns. Read against the section below, the lotus explains the shape of the roof shells and the 12 feature columns; it does not explain the 17 mega columns, the concrete frame or the plan, which follow the demands of an airport.
Compare Delhi's Bahá'í House of Worship, where the concrete petals are structure, roof and walls at once (see our Lotus Temple case study). At Navi Mumbai the petals are a roof canopy held up by a separate system of columns, which is why it can read as floating.
ZHA's drawings are not public in full, so the plan below is MOA's reading of published descriptions, not the layout. Arup describes a headhouse built on a repeating structural grid, with the roof's grid turned 45 degrees to make an open internal area, and piers and boarding bridges of a shared modular design. Surfaces Reporter (13 October 2025), which lists ZHA's team, describes the central atrium as a symbolic pond that anchors the concourses radiating from it. The ACI article says the feature columns also guide passenger movement, so the columns double as wayfinding.
The phasing explains the modular approach. The Adani release gives 20 million passengers and 0.5 million tonnes of cargo a year for the first phase, rising to 90 million passengers. The Moodie Davitt Report gives Terminal 2 at 30 million passengers in 2029 and Terminal 3 in 2032; Ceccato told the Free Press Journal that Terminal 2 was due by 2030. Plans have also grown: Dezeen reported 60 million passengers a year in 2018, the 2025 compliance report still states 60 million as the ultimate capacity under the current clearance, and the operator now gives 90 million. Sources also differ on runways at full build-out: the clearance describes two parallel runways of 3,700 m, while ZHA's page and the Adani release mention four.
The roof rests on two kinds of column. The Adani release and the ACI article give 12 sculptural feature columns and 17 mega columns. The ACI article describes the feature columns as hollowed "to allow daylight to cascade through", and the mega columns as carrying the weight of the canopies over wide spans without columns in the middle of the concourse, which is what lets the roof appear to float. Surfaces Reporter and Parametric Architecture (Isha Chaudhary, 11 October 2025) both give the roof as about 370 m long; neither ZHA's page nor Arup's gives a figure, so treat it as reported.
Arup's page adds the engineering logic. "Branching columns, which can support larger spans than straight columns" made the petal forms possible, and the structure uses "less than 100kg of steel per m2". Mumbai's moderate seismic risk meant the concrete frame and the roof were designed to act together in an earthquake. The ACI article adds that the curved petals were shaped to shed monsoon rain and reduce wind resistance.
Speed shaped the construction. Arup describes a fast-track design-and-build contract, with site clearance starting while design was still under way. Its facade is a modular system of prefabricated units, which Arup says sped up installation and improved site safety, and ribbed concrete slabs were used to cut carbon. Arup also reports that the contractor "did not submit a single request for clarification", a claim worth reading as the engineer's own.
The roof combines a steel superframe and prefabricated modular steel roof units with reinforced concrete cores, according to Surfaces Reporter. L&T's page describes the petals as GFRG (glass-fibre reinforced gypsum) and lists 3D design with automated grading, drone surveys and IoT monitoring among its methods. The ACI article says each petal needed bespoke moulds, modular prefabrication and "millimetre-level precision". CNN's report mentions jaali latticework in the interiors.
Daylight comes from above. Surfaces Reporter describes continuous skylight strips in the roof petals, "optimized through solar-angle modeling", and the hollow feature columns act as light wells. The lighting design is credited to Lichtkompetenz and Lum Gallery on LSI's project page.
The environmental figures are design claims and commitments, not measured results. The Adani release lists passive cooling, natural light, solar power and rainwater harvesting. The compliance report says Terminal 1 is "in process of getting LEED BD+C V4 Certification" and that a preliminary energy assessment shows savings of more than 20%; Arup's page says the project targets LEED Gold. The same report plans about 15.3 MW of solar power for phases 1 and 2, rising to 22.14 MW at the final phase, and says rainwater harvesting is planned by the final phase. We found no published measured energy or comfort study. For how these ratings work, see our guide to green building certification in India.
Coverage at the opening dwelt on the lotus roof; the practical questions concern access, the land works and cost.
These are our reading, not the architects' claims.
Studying it for a thesis? Our case-study documentation guide sets out what to record on a site visit.
The terminal is a working airport, so its interior is seen by flying. The official airport website has flight information and a getting-to-the-airport page covering taxis, app cabs, car rental and parking. It publishes no entry arrangement for non-passengers. ZHA's photographs are on its project page.
Want a building that works this hard for its site? Find an architect on MOA.
Zaha Hadid Architects of London designed Terminal 1, the control tower and landside access after winning a 12-week competition in March 2018. Arup provided engineering for the concept and scheme designs, and Larsen & Toubro was the EPC contractor.
Yes, by the architects' and operator's own account. ZHA says the forms are informed by the lotus, the roof shells read as petals, the 12 feature columns are flared like petals and the central atrium is described as a lotus pond.
It was inaugurated on 8 October 2025 (L&T's page says 8 September 2025). Commercial flights began on 25 December 2025, and international flights on 15 July 2026.
The first phase is designed for 20 million passengers and 0.5 million tonnes of cargo a year, rising to 90 million passengers a year at full build-out, by the operator's figures.
The Adani Group calls it a Rs 16,700 crore PPP; the Maharashtra Pollution Control Board's 2022 consent gives a capital investment of Rs 19,647 crore for phases 1 and 2.